Home Top Stories These are the eleven streets of Córdoba that are already undergoing renovation...

These are the eleven streets of Córdoba that are already undergoing renovation work or will begin immediately

23
0
These are the eleven streets of Córdoba that are already undergoing renovation work or will begin immediately

He Mayor of Infrastructure of the Cordoba City Council, Miguel Ruiz Madruga, appeared this Tuesday to make balance actions of street reform of which the Council is in progress – four – and the one which will begin soon – seven others -.

He first package of renovations It is made up of roads already under construction in Alcalde de la Cruz Ceballos; Crossing the Miño; Calatañazor and the Dawn of Fátima. In total, they have a budget of 637,386 euros.

Inside second grouphe explained, there are streets in which will intervene “immediately”. “By the end of the year, because these are projects that have already been signed, although some are waiting for the health and safety plan to be able to start the work,” said Ruiz Madruga. It will take place in Juan Latino (second phase); ; Bishop Ascargorta; Luis Ponce de Leon; Calle del Campo (second phase); the sculptor Pedro de Paz; Golondrien and San Juan Bautista de Lasalle [todos los detalles de estas actuaciones y de las que ya han arrancado en la ficha que acompaña la información]. He cost of these reforms addition 1.96 million. Among the works which will start and those which are already in progress, the The municipal council will invest 2.6.

  • Mayor of Cruz Ceballos (in execution): Its budget is 291,917.5 euros and will last three months.

  • Crossing the Miño (in progress): Its cost is 47,829 euros and the improvement work will last two months.

  • Calatañazor (in execution): The disbursement to be made will be 260,632 euros and the execution time is three months.

  • Dawn of Fatima (in execution): The budget is 37,007 euros and the duration of the reform is two months.

  • Second phase of Juan Latino (from now on everything start before the end of the year): The cost will be 155,920 euros and the work will last three months.

  • Bishop Ascargorta: The investment will be 385,551 euros and the execution time will be three months.

  • Luis Ponce de Leon: The disbursement to be made by the Town Hall will amount to 497,999 euros and the work will last six months.

  • Second phase of Campo Street: The budget is 241,262 euros and the renovation period is three months.

  • Sculptor Pedro de Paz: The amount of the renovation will be 447,127 euros and the action will last four months.

  • Swallow: The cost will be 189.10 euros and the execution time of the work will be three months.

  • Saint John the Baptist of Lasalle: The budget is 41,655 euros and the work will last one month.

He Mayor of Infrastructure provided this information on the ground. Because he appeared in the Calatañazor Streetwhich is currently being renovated and which, Ruiz Madruga emphasized, was “a historic claim of Valdeolleros“. “It was a very poor road and action also needed to be taken. “It was very, very, very necessary,” he assured.

Comprehensive intervention in Calatañazor

It’s a “global” intervention. The infrastructure will renew the sidewalk and the road. It will also be necessary to act on lighting and put in trees. Ruiz Madruga emphasized that they began “the journey to unblock the thrombus that we had” for the execution of actions in his department. “We had many actions which were already in preparation and others which were already in project and which had to be launched by launching them by call for tenders. We are already starting to see the results,” he said, ignoring the memory that the last term was eventful in this delegation – the infrastructure affair, which continues before the courts which will determine whether there was corruption, completely shook it.

Ruiz Madruga defended that it is “very important, due to the state in which a large part of our city is, that not only do we do good maintenance, but that we do coherent street reform plan“. In this sense, he emphasized that “we are doing something to which we are also committed and which is also important.”

It is, he explained, “try to exercise“. “That is to say, the projects that we have already defined to be executed next year will be carried out the previous year,” he stressed. Regardless of which party governed, continued this member of the municipal government, what happened in this delegation was that there was an “abnormal” operationwith which you are currently carrying out a project which is committed, perhaps, in 2020. This, he warned, generates “technical problems because the costs during the execution of the works are not those which have took place at the time the action in question was drawn up.

LEAVE A REPLY

Please enter your comment!
Please enter your name here